Ground-Mounted Photovoltaics 2026: Planning, Approving, and Building a Solar Farm
Ground-mounted photovoltaic systems are driving Germany’s solar expansion: In the first half of 2026, ground-mounted systems accounted for just over half of all newly installed capacity. This page explains the costs and revenue generated per hectare by ground-mounted photovoltaic systems, which areas are suitable, what legal framework applies, and how a solar farm is developed—from site assessment to grid connection. All figures include their sources and dates.
Go directly to the topic that interests you: You own a plot of land · You want to invest · You represent a municipality
Table of Contents
- Ground-Mounted Solar Power in Numbers: What One Hectare Yields
- What is an open-field solar power plant?
- Which areas are suitable for ground-mounted solar panels?
- Legal Framework for Ground-Mounted Photovoltaic Systems
- Building a Solar Farm: The Process
- How much does a solar farm cost?
- Compensation: Tender or PPA
- Financing Ground-Mounted Solar Power Systems: KfW and Taxes
- For Landowners: Lease Out Your Land Instead of Building Yourself
- For Investors: Returns and Ownership
- Local Communities, Nature, and Acceptance
- Why Logic Energy
- Frequently Asked Questions
- Sources and Notes
Ground-Mounted Solar Power in Numbers: What One Hectare Yields
Anyone interested in ground-mounted photovoltaic systems usually wants to know first whether the site or the project is financially viable. The calculation is straightforward. Fraunhofer ISE estimates the installation density of modern systems at around 1 MW per hectare, with module efficiencies of about 22 percent. According to the ISE study on levelized cost of electricity from July 2024, the investment costs for ground-mounted systems starting at 1 MWp range from 700 to 900 euros per kilowatt-peak.
When it comes to yield, Fraunhofer ISE distinguishes between two metrics. In the reference case (irradiance of 1,270 kWh per square meter of module area, performance ratio of 85 percent), approximately 1,080 full-load hours are physically available. According to the transmission system operators’ trend scenario for 2026, only 864 full-load hours are usable, with a continuing downward trend because systems are curtailed during periods of negative prices and grid congestion.
| Key figure per hectare | Value | Basis |
|---|---|---|
| Installed capacity | about 1 MW | Fraunhofer ISE, Current Facts, Version August 20, 2026 |
| Investment | 700,000–900,000 euros | 700–900 €/kWp, Fraunhofer ISE, July 2024 |
| Electricity output | 864,000–1,000,000 kWh/year | 864 usable full-load hours (ÜNB 2026) up to 1,000 kWh/kWp |
| Calculated Proceeds | approximately 41,400–47,900 euros per year | Adjudication price: 4.79 ct/kWh; bidding deadline: July 1, 2026 |
| Fixed Operating Costs | about 13,300 euros per year | 13.3 €/kW·a, ISE model assumption, excluding decommissioning |
| As of September 22, 2026. Calculated by the author based on the sources cited. | ||
The award value is a target value used in the market premium model; it is not a guaranteed price. During hours when exchange prices are negative, the subsidy is not paid. Our article “Solar Park Return on Investment in 2026: How to Calculate from Hectares to IRR Step by Step” explains how to calculate the return on investment after accounting for operating costs, decommissioning reserves, and financing.
What can your space accommodate?
We'll run the numbers for your location based on these figures: power output, investment requirements, grid connection, and the permitting process. Free of charge and with no obligation.
What is an open-field solar power plant?
In common usage, the terms “ground-mounted photovoltaic systems,” “ground-mounted PV,” “solar park,” and “ground-mounted solar plant” all refer to the same type of system; government agencies and technical documents often abbreviate “ground-mounted photovoltaic systems” as “PV-FFA.” Because there is no roof to dictate the orientation, the modules can be freely oriented toward the south or in an east-west direction. Open-field systems differ from related designs primarily in terms of cost and the subsidy process.
| Design | Investment per kWp | Land Use | Typical application |
|---|---|---|---|
| Ground-mounted solar power plant with a capacity of 1 MWp or more | 700–900 euros | Area for electricity generation | Tenders Issued by the Federal Network Agency |
| Agri-photovoltaics (0.5–2 MWp) | 900–1,700 euros | Farming Continues | The agricultural status of the land should be maintained |
| Large rooftop solar array | 900–1,600 euros | no competition for space | Commercial and Industrial Roofs for Self-Consumption |
| Source: Fraunhofer ISE, Study on the Levelized Cost of Electricity from Renewable Energy Sources, July 2024. | |||
PV-FFA systems with a capacity of more than 1 MW are eligible for subsidies under the Renewable Energy Sources Act (EEG) only through a premium awarded in tenders issued by the Federal Network Agency. Our overview of photovoltaic systems shows which system type suits which profile; the page on agri-photovoltaics covers combined use with agriculture.
Which areas are suitable for ground-mounted solar panels?
For ground-mounted PV, the following applies: The size of the project determines how the fixed costs for planning, expert reports, zoning plans, and grid connection are distributed per kilowatt-peak. The grid connection determines whether a project can be connected economically at all: The closer a substation with available capacity is located, the shorter and less expensive the power line will be. The subsidy framework determines whether the site is eligible to participate in EEG tenders, and its protected status determines whether it can be approved at all.
According to the rule of thumb in the C.A.R.M.E.N. guidelines for ground-mounted solar power plants (as of March 2023), a plant in Bavaria requires an average of about 10 square meters per kilowatt-peak, or roughly 1 hectare per MWp. An area of five hectares can therefore accommodate a solar farm of about five MWp.
Suitable
- Cultivated land, grassland, fallow land, or other undeveloped land in a contiguous area of approximately 5 hectares or more
- Substation with available capacity nearby
- Area covered by the EEG subsidy framework
- Access road suitable for vehicle traffic during the construction phase
Especially good
- 200-meter strips along highways or double-track railroad lines
- Conversion Areas and Sealed Areas
- gentle slope, no shade
Not suitable
- Natura 2000, nature reserves, legally protected biotopes
- drained peat soils (excluded from the request for proposals)
- Areas without an accessible utility connection
Landowners who want to lease their land rather than build on it themselves can find information on how lease rates are calculated on our page about leasing land for solar parks.
Legal Framework for Ground-Mounted Photovoltaic Systems
According to Section 35(1)(8)(b) of the German Building Code (BauGB), solar installations on land along highways and rail lines of the primary network with at least two main tracks are given priority up to a distance of 200 meters, measured from the outer edge of the roadway. In such locations, the project does not require its own zoning plan, provided that there are no conflicting public interests. Outside this strip, the process requires a municipal zoning plan, which often also necessitates an amendment to the land-use plan. The municipality thus plays a key role in determining whether and where ground-mounted PV systems are built.
Section 37(1)(2) of the EEG specifies the types of land on which bids are permitted: among other things, already sealed land, converted land, land along highways and railways up to 500 meters, and arable or grassland in disadvantaged areas. Drained peatlands are excluded. The states may exclude disadvantaged areas pursuant to Section 37c of the EEG by statutory order; according to the Federal Network Agency, no state government had issued such an order as of the bidding deadline of July 1, 2026.
It is important to distinguish between the two corridors: The 200-meter strip under the BauGB pertains to permitting, while the 500-meter corridor under the EEG pertains to eligibility for subsidies. An area between 200 and 500 meters is eligible for subsidies but requires a zoning plan.
Highway Law: The Federal Highway Authority is involved
Section 9(2c) of the Federal Highway Act (FStrG) expressly exempts facilities for generating electricity from solar radiation from the prohibition on construction along federal highways. Nevertheless, the Federal Highway Authority or the highest state road construction authority must be consulted if the facility is to be constructed within 100 meters of a highway or within 40 meters of the outer edge of the paved roadway on a federal highway outside a built-up area. If the facility does not require a permit, the project developer must notify the authorities before construction begins.
Biodiversity: three out of five criteria
Since the introduction of Solar Package I, bids for ground-mounted systems under Section 37(1a) of the EEG must meet at least three of five criteria:
- The modules occupy no more than 60 percent of the project's floor area,
- a management approach that promotes biodiversity, such as mowing no more than twice a year with removal of the cut material or adapted grazing,
- Connectivity for animals: wildlife corridors for large mammals where the side lengths exceed 500 meters, and underpasses for smaller species,
- site-specific biotope elements covering at least 10 percent of the facility's area,
- Soil-conserving farming practices without the use of pesticides or fertilizers; cleaning agents are biodegradable and used only when necessary.
These criteria are prerequisites for the bid and must therefore be incorporated into the space and cost planning from the very beginning.
Building a Solar Farm: The Process
- Site inspection — size, utility connections, access for heavy equipment, conservation status. In our experience, this takes one to four weeks.
- Land Acquisition — Lease or Option Agreement with the Owner.
- Urban Land-Use Planning — Resolution to Initiate Planning, Environmental and Species Protection Assessment, Public Participation, Resolution to Adopt the Plan. Within the designated 200-meter strip, the zoning plan does not apply.
- Tender — Submit a bid to the Federal Network Agency on one of the three bidding dates: March 1, July 1, or December 1 (Section 28a(1) of the Renewable Energy Sources Act (EEG)), or alternatively, enter into a power purchase agreement.
- Construction and Grid Connection — Mounting Structure, Modules, Inverters, Transfer Station, Cable Route.
- Operations — technical and administrative management, landscaping, and monitoring for over 20 years.
Land-use planning, species conservation, and grid connection proceed in parallel and are mutually dependent. Those who submit their grid connection request only after the zoning plan is finalized lose time; those who complete species conservation mapping too late may, in some cases, lose an entire growing season. Based on our observations, municipalities with experience in solar park procedures are significantly faster than those drawing up their first zoning plan for an open-space solar facility.
Grid connection is the second critical path. Many suitable sites are located in rural areas, where grid capacity is often limited; the grid operator assesses whether its grid can accommodate the additional electricity. The grid connection request must therefore be the first step in any planning process. Smaller wind farms connect to the distribution system operator’s medium-voltage grid, while large projects connect to the high-voltage grid. An experienced project developer will reject sites for which he sees no realistic possibility of connection—this protects owners from contracts that remain inactive for years without a project.
How much does a solar farm cost?
| Cost Breakdown | Value | Source |
|---|---|---|
| Investment in ground-mounted systems starting at 1 MWp | €700–900 per kWp | Fraunhofer ISE, July 2024 |
| Agri-PV Investment, 0.5–2 MWp | 900–1,700 €/kWp | Fraunhofer ISE, July 2024 |
| Fixed Operating Costs for Open Space | 13.3 €/kW·a (model assumption) | Fraunhofer ISE, July 2024 |
| Electricity Generation Costs in the South | 4.1–5.0 ct/kWh | Fraunhofer ISE, July 2024 |
| Electricity Generation Costs in the North | 5.7–6.9 ct/kWh | Fraunhofer ISE, July 2024 |
| Source: Fraunhofer ISE, Study on Levelized Cost of Electricity from Renewable Energy Sources, July 2024. A more recent edition is not available. | ||
The total investment includes modules, inverters, the mounting structure, civil engineering, grid connection, and planning. Two items are often omitted from many rough estimates. First, decommissioning: ISE operating costs explicitly exclude this, and regulatory authorities typically require a security deposit for it—usually a bank guarantee. Second, grid connection, which can account for a significant portion of the investment depending on the distance to the substation.
The levelized cost of electricity shows why ground-mounted solar farms are the most cost-effective form of solar power generation: Thanks to economies of scale, standardized support structures, and ground-level installation, their costs are lower than those of large rooftop PV systems and new fossil fuel power plants. You can find the complete profitability analysis—including operating costs, decommissioning, and IRR—in the article on solar farm returns.
Compensation: Tender or PPA
Ground-mounted systems with a capacity of more than 1 MW are subsidized through the Federal Network Agency’s tenders for solar power plants in the first segment. The bidder with the lowest bid is awarded the contract first; the bid amount becomes the applicable rate for 20 years.
| Bidding deadline | Ø volume-weighted premium value | Range of surcharges |
|---|---|---|
| 01.07.2026 | 4.79 ct/kWh | 4.38–4.97 ct/kWh |
| 01.03.2026 | 4.94 cents per kWh | 3.99–5.10 ct/kWh |
| 01.12.2025 | 5.00 cents per kWh | 4.40–5.30 ct/kWh |
| Source: Federal Network Agency, Completed Solar Power Plant Auctions—First Segment. As of September 22, 2026. The bid deadline of December 1, 2026, had not yet been announced at that time. | ||
The maximum value is capped
The maximum value is calculated based on the previous rounds in accordance with Section 37b(1) of the EEG, but may not exceed 5.9 cents per kilowatt-hour. A project proposal that assumes rising bid prices beyond this cap is inconsistent with the text of the law.
PPA as an Alternative
Instead of participating in the auction, the operator can sell the electricity through a Power Purchase Agreement (PPA). enervis’s PPA price tracker shows that a ten-year solar PPA with a “pay as produced” structure, including certificates of origin, ranges from 28 to 40 euros per megawatt-hour, based on calculations for August 2026. This is significantly below the winning bid price from the July round. Our article on the CfD requirement starting in 2027 explains the subsidy framework that will apply from that year onward; the guide to EEG remuneration in 2026 explains all remuneration rates.
Financing Ground-Mounted Solar Power Systems: KfW and Taxes
| Term / Interest-Only Period / Fixed-Rate Period | Interest Rate | Effective interest rate |
|---|---|---|
| 5 / 1 / 5 years | 4,63 % | 4,72 % |
| 20 / 3 / 10 years | 4,94 % | 5,03 % |
| 30 / 5 / 10 years | 4,95 % | 5,04 % |
| Source: KfW Terms and Conditions Guide, Program 270; interest rates effective as of September 17, 2026. | ||
Solar parks fall under the “without rooftop PV” option; the more favorable rooftop option applies only to rooftop systems. KfW specifies a maximum rate for each price category; the actual interest rate depends on creditworthiness and collateral and is determined at the time of approval. The terms and conditions may change within a matter of days. The application is submitted through the borrower’s primary bank and must be filed before the project begins.
From a tax perspective, declining-balance depreciation is the most important tool. For movable assets acquired after June 30, 2025, and before January 1, 2028, Section 7(2) of the German Income Tax Act (EStG) allows for three times the straight-line depreciation rate, up to a maximum of 30 percent. With a useful life of 20 years, this amounts to 15 percent per year for plant equipment. The investment deduction and special depreciation under Section 7g of the German Income Tax Act (EStG), of up to 50 and 40 percent, respectively, are available only to businesses with profits of up to 200,000 euros and rarely play a role for typical project companies.
Logic Energy is not a financial or tax advisor. For tax classification, we will refer you to an independent advisor from our network of partners—this advisor, not us, will conduct the initial consultation.
Our article on photovoltaics and taxes explains how these tools can be combined in specific cases.
For Landowners: Lease Out Your Land Instead of Building Yourself
For the owner, three things matter: the amount of the lease payment, its security over the term of the lease, and the clauses that apply in the event of demolition, insolvency, or sale. These include indexation, a demolition guarantee, the registration of an easement in the land registry, and clear rules for renewal options. For tax purposes, the lease is classified as income from renting and leasing; the land may lose its agricultural status for inheritance tax purposes.
You can find the complete breakdown of the lease payment per hectare, the contract terms, and the tax pitfalls on our page “Leasing Land for a Solar Farm.” We’ll evaluate your land for free using the form at the bottom of this page.
For Investors: Returns and Ownership
The calculation chain starts with the hectare, moves through power output and yield to revenue, subtracts operating costs and the decommissioning reserve, and ends with the IRR. Our article on solar park returns uses various scenarios to illustrate how sensitive the result is to premium value, full-load hours, and the cost of capital. Our page on PV investments provides an overview of direct PV investments as an asset class.
Investments in ground-mounted solar projects are entrepreneurial investments that involve risks: bid and market price risk, curtailment, permitting and construction timeline risk, interest rate risk, and follow-on financing risk. The contracting party for Logic Energy is mediplan Helm e.K.; as a registered merchant, the owner is personally and fully liable in accordance with Sections 1, 17, and 19 of the German Commercial Code (HGB). Investments are possible starting at 100,000 euros.
Local Communities, Nature, and Acceptance
Under Section 29(1)(2)(a) of the Trade Tax Act (GewStG), nine-tenths of the trade tax for solar parks is calculated based on installed capacity and one-tenth based on wages—meaning the host municipality receives the majority of the tax, even if the operator is based elsewhere. Participation under Section 6(1)(2) and (3) of the Renewable Energy Sources Act (EEG) is voluntary. For a park that feeds 50 gigawatt-hours into the grid annually, this can amount to up to 100,000 euros per year.
Ground-mounted solar power plays a major role in the expansion of renewable energy and reduces greenhouse gas emissions from electricity generation. A comparison of land use also favors ground-mounted solar. According to an analysis cited by the Center of Excellence for Nature Conservation and the Energy Transition, one hectare of ground-mounted PV meets the annual electricity needs of about 230 households, while one hectare of corn grown for biogas meets the needs of seven.
A study by the industry association bne from March 2025 examined 30 solar parks in ten federal states and identified 385 plant species, 36 butterfly species, 30 grasshopper species, and 32 breeding bird species. According to the authors, the maintenance of the site was a decisive factor. However, there are valid objections to this: competition for land with food production, changes to the landscape, and habitat loss when sensitive biotopes are built over. For this reason, the EEG excludes drained peatlands and Natura 2000 sites in disadvantaged areas and mandates biodiversity criteria. In the zoning plan process, demonstrable ecological enhancement is often the argument that secures acceptance within the community. Our analysis of photovoltaic expansion in Germany provides context for how this expansion is developing overall.
Why Logic Energy
Personal liability of the owner
The contracting party is mediplan Helm e.K.; the owner is personally and fully liable in accordance with Sections 1, 17, and 19 of the German Commercial Code (HGB).
Active land acquisition
We look for properties and inspect them ourselves. You'll receive an initial assessment within four weeks.
Everything under one roof
Site acquisition, permitting, construction, and operations management throughout the entire project term.
The Group's Experience
The Helm Group supports photovoltaic projects in Germany and Italy.
Have the property appraised or invest?
Please send us the location and size of your property, or contact us to discuss participating in an open-space project. You’ll receive a detailed assessment—free of charge and with no obligation.
Logic Energy Editorial Team
Frequently Asked Questions
At what size does an open-space system become worthwhile?
There is no one-size-fits-all figure. We generally start with about five hectares of contiguous land; depending on the grid connection and the layout of the property, three hectares may also be sufficient. The key factor is how the fixed costs for planning, permitting, and grid connection are distributed across the output.
How much land does one megawatt require?
About one hectare. Fraunhofer ISE cites a density of around 1 MW per hectare for modern systems, while the C.A.R.M.E.N. guidelines indicate an average of about 10 square meters per kilowatt-peak in Bavaria.
How much does a solar farm cost per hectare?
According to Fraunhofer ISE (July 2024), ground-mounted solar power plants with a capacity of 1 MWp or more cost between 700 and 900 euros per kilowatt-peak. At approximately 1 MW per hectare, that amounts to 700,000 to 900,000 euros, excluding decommissioning costs.
Which areas are eligible for subsidies under the EEG?
Section 37(1)(2) of the EEG lists, among other things, sealed areas, converted areas, areas along highways and railroads up to 500 meters, and arable land and grassland in less-favored areas. Drained peatlands are excluded.
What does the 200-meter strip in the BauGB regulate?
As of January 11, 2023, solar installations extending up to 200 meters along highways and rail lines with at least two main tracks in rural areas are given preferential treatment (Section 35(1)(8)(b) of the German Building Code (BauGB)). No separate zoning plan is required in these areas.
What will the surcharge amount be in 2026?
At the bidding session on July 1, 2026, the volume-weighted winning bid was 4.79 ct/kWh, with a range of 4.38 to 4.97 ct/kWh. The maximum value of 5.90 ct/kWh is capped by law under Section 37b(1) of the EEG.
How long does it take to build a solar farm?
Based on our project experience, the zoning plan takes six to twelve months, and the entire development process—from site evaluation to commissioning—takes two to four years. In the designated 200-meter strip, a zoning plan is not required.
Sources and Notes
All sources were accessed on September 22, 2026.
- Federal Network Agency — Bidding deadline: July 1, 2026, solar power plants, first segment: winning bid price 4.79 ct/kWh, range 4.38–4.97 ct/kWh, maximum price 5.90 ct/kWh; no state regulation pursuant to Section 37c(2) of the EEG: https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/Ausschreibungen/Solaranlagen1/01072026/artikel.html
- Federal Network Agency — Completed Solar Power Plant Tenders, First Segment: Award Series, Coverage Rate 148.51 Percent: https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/Ausschreibungen/Solaranlagen1/BeendeteAusschreibungen/start.html
- pv magazine, July 15, 2026 — Analysis by the Federal Network Agency on new installations in the first half of 2026 (data as of July 13, 2026): 7,394.4 MW total, of which 4,010.4 MW came from 1,002 ground-mounted systems: https://www.pv-magazine.de/2026/07/15/bundesnetzagentur-erwartet-netto-zubau-von-1268-megawatt-im-juni/
- § 35 of the German Building Code (BauGB) — Construction in Outlying Areas, Paragraph 1, No. 8, Subparagraph b: https://www.gesetze-im-internet.de/bbaug/__35.html
- Section 6 of the EEG — Financial Participation of Municipalities: https://www.gesetze-im-internet.de/eeg_2014/__6.html
- Section 28a of the EEG — Tender Volume and Bidding Deadlines for Solar Power Plants in the First Segment: https://www.gesetze-im-internet.de/eeg_2014/__28a.html
- § 37 EEG — Bidding Rules for Solar Power Plants in the First Segment, Paragraph 1, No. 2, and Paragraph 1a: https://www.gesetze-im-internet.de/eeg_2014/__37.html
- § 37b EEG — Maximum value for solar installations in the first segment: https://www.gesetze-im-internet.de/eeg_2014/__37b.html
- § 37c EEG — Exclusion of Bids in Disadvantaged Areas: https://www.gesetze-im-internet.de/eeg_2014/__37c.html
- § 9 FStrG — Structures on Federal Highways, Paragraph 2c: https://www.gesetze-im-internet.de/fstrg/__9.html
- § 29 of the Trade Tax Act (GewStG) — Allocation Criteria: https://www.gesetze-im-internet.de/gewstg/__29.html
- § 7 EStG — Depreciation Allowance, para. 2: https://www.gesetze-im-internet.de/estg/__7.html
- § 7g of the Income Tax Act (EStG) — Investment Deductions and Special Depreciation Allowances: https://www.gesetze-im-internet.de/estg/__7g.html
- KfW Rate Guide, Program 270 — Interest rates effective as of September 17, 2026: https://www.kfw-formularsammlung.de/KonditionenanzeigerINet/KonditionenAnzeiger?ProgrammNameNr=270
- Fraunhofer ISE — Levelized Cost of Electricity for Renewable Energy, July 2024: Capital Costs, Levelized Cost of Electricity, Operating Costs: https://www.ise.fraunhofer.de/content/dam/ise/de/documents/publications/studies/DE2024_ISE_Studie_Stromgestehungskosten_Erneuerbare_Energien.pdf
- Fraunhofer ISE — Current Facts on Photovoltaics in Germany, Version August 20, 2026: Irradiance Density, Full-Load Hours: https://www.ise.fraunhofer.de/content/dam/ise/de/documents/publications/studies/aktuelle-fakten-zur-photovoltaik-in-deutschland.pdf
- C.A.R.M.E.N. e.V. — Guidelines for Open-Space Installations, as of March 2023: Space Requirements: https://www.carmen-ev.de/wp-content/uploads/2022/04/Leitfaden_Freiflaechenanlagen.pdf
- enervis PPA Price Tracker via pv magazine, September 7, 2026: Solar PPA 28–40 €/MWh: https://www.pv-magazine.de/2026/09/07/enervis-ppa-price-tracker-fuer-photovoltaik-ppa-preise-weiter-im-aufwaertstrend/
- Center of Excellence for Nature Conservation and the Energy Transition — Land-Use Efficiency of Renewable Energy for Electricity Generation: https://www.naturschutz-energiewende.de/fragenundantworten/flaecheneffizienz-erneuerbarer-energien-zur-stromerzeugung/
- bne — Study “Biodiversity in Solar Parks,” March 26, 2025: https://www.bne-online.de/bne-pressemitteilung-studienveroffentlichung-artenvielfalt-im-solarpark/
Do you own unused land and want to lease or sell it long-term? With ground-mounted solar panels, you can turn idle or low-yield land into a predictable source of income!
Your benefits:
Long-term, predictable lease income or solar power revenue
If you lease the property, you remain the owner
No more management costs
Increase in the value of the property
Ecological enhancement
No soil sealing
Potential for dual use
Contribution to the energy transition
What types of land are suitable?
Generally suitable:
Farmland with low productivity (marginal soils)
Grassland with poor soil quality
Brownfield sites (former military, commercial, or industrial sites)
Areas along highways and railroad tracks (200-meter-wide strips)
Wasteland, gravel pits, landfills (after remediation)
Not suitable:
Nature reserves
Sites designated as historic landmarks
Areas with heavy shade
Areas in floodplains (without special measures)
For landowners:
DO YOU HAVE LARGE PARCELS OF LAND TO SELL OR LEASE?
FOR INVESTORS:
INDUSTRIAL SOLAR PARKS AS AN INVESTMENT
Are you interested in investing in large-scale solar projects? With our open-field model, you can invest in professionally developed solar parks ranging from 30 MWp to utility-scale projects exceeding 250 MWp. We manage the entire value chain—from project development, site acquisition, and permitting to EPC and long-term operations.
What you get:
Ready-to-build projects with guaranteed land availability
Full-scale project development: site analysis, permitting process, grid connection, financing structure
EPC Services (Engineering, Procurement, Construction): We build your turnkey facility to the highest quality standards
Long-term operation (O&M): 20–40 years of professional management, maintenance, insurance, and monitoring
Investment in inverters starting at €100,000 or acquisition of entire solar farms