Solar Power Systems with Battery Storage: What Co-Location Means for Return on Investment, Self-Consumption, and Cost-Effectiveness
Co-location connects a photovoltaic system and a battery storage system behind a shared grid connection and increases the project's IRR by approximately 29%—through shared infrastructure costs, not through additional revenue.
The short answer
A co-located battery storage system—the combination of a photovoltaic system and battery storage at the same location—has become a key differentiator in the German solar market by 2026. This article is aimed at companies seeking to reduce their electricity costs by installing their own PV system with storage, as well as investors who want to maximize the return potential of a combined PV-storage project—featuring concrete figures, up-to-date market data, and a clear overview of the regulatory window from 2026 to 2028.
A photovoltaic system without storage leaves money on the table today: Electricity fed into the grid at noon generates lower revenues than electricity that can be drawn during peak demand periods. While standalone PV systems will struggle with a declining solar capture rate and 573 hours of negative electricity prices in 2025, an integrated energy storage system turns precisely these market conditions into a structural advantage.
1. Market Data: 25.5 GWh Installed—and That's Just the Beginning
The German market for PV storage is growing faster than any other sector of the energy industry. Installed storage capacity has increased fivefold in five years. At the same time, more than 80% of all newly installed photovoltaic systems on single-family homes are already combined with solar storage—a clear sign that the market is mature.
The structural shift in new construction shows where things are headed (RWTH Aachen / ISEA, January 2026):
| Segment | Expansion 2025 | Change from 2024 |
|---|---|---|
| Residential Storage (≤30 kW) | 4.19 GWh | −6,4 % |
| Large-scale storage (>1 MW) | 2.02 GWh | more than doubled |
| Commercial Storage (30–1,000 kW) | 0.36 GWh | +47 % |
This is due to a historical investment backlog. In November 2025, the Federal Network Agency reported approximately 400 GW / 661 GWh in grid connection requests for large-scale storage systems from transmission system operators alone; according to a BDEW survey, which includes distribution system operators, the figure exceeds 720 GW. In contrast, only 2.4 GW are currently in operation.
This bottleneck points to the real issue: grid connection. Available grid connection points are scarce, the grid connection approval process is protracted, and connections are often available to new projects only for a limited time. This is exactly where co-location comes in—it makes use of an existing grid connection for the generation facility. BSW-Solar estimates that the required storage capacity by 2030 will be around 100 GWh—four times the current level.
2. Co-location: Where the 29% project IRR comes from
For new installations, the IRR advantage does not stem from additional revenue generated by the storage system, but rather from the shared infrastructure: grid connection, cable route, and substation are jointly funded through a cable-pooling model. With a design ratio of 1:1:0.5 (grid connection point to PV to storage), the PV project theoretically bears only about two-thirds of these costs. Self-consumption optimization and peak shaving are not included in the model: The modeled storage system is a “gray electricity” storage system that charges exclusively from the grid and is accounted for separately. The storage system also generates its own revenue from balancing energy and arbitrage trading between low- and high-price periods. We discuss the mechanics of arbitrage trading in detail in our analysis of PV-storage arbitrage returns.
- New investments: relative increase in the project IRR of approximately 29%—from 8% to about 10% in the example calculation
- Existing systems with retrofitted energy storage: +6–24% relative, depending on investment cost and revenue assumptions; based on 15%, this corresponds to approximately 16 to 19%
- Unfavorable revenue scenario: only the infrastructure benefit of about 6% remains; under very unfavorable assumptions, the additional benefit disappears entirely
- Revenue reduction due to the shared grid connection point: approximately 3.5–4%—this applies to the storage system compared to stand-alone operation, not to the PV system
The authors explicitly state that their figures are indicative. 8Energies, enspired, and GOLDBECK SOLAR are themselves active in the market for co-location projects: a primary source, but not an independent one.
3. Co-Location vs. Stand-Alone Battery Storage: Models and Use Cases
| Feature | Co-location storage | Standalone Storage |
|---|---|---|
| Power Connection | shared with the power plant | a close call of their own |
| Power source | Combined PV/wind power (green electricity) | Grid + Market (also Multi-Use) |
| Main Revenues | Self-Consumption, Peak Shaving, Arbitrage | Arbitrage, Balancing Power, System Services |
| Approval / Costs | bundled, more affordable | independently |
| Flexibility | linked to production | maximum |
Stand-alone storage: Operated solely on the market
A stand-alone battery storage system does not feed its own solar or wind power into the grid, but rather generates revenue through battery trading: arbitrage on the day-ahead and intraday markets, as well as balancing energy (FCR, aFRR, and—increasingly important starting in 2026—the minute reserve). Stand-alone operation offers maximum flexibility but requires its own grid connection—and that is precisely where the bottleneck lies. As demand for grid-stabilizing system services continues to rise starting in 2026, the market environment remains attractive; however, revenues in individual markets fluctuate significantly and require active cross-market optimization by an experienced marketer.
Co-location Facilities: Storage for Solar or Wind Power
In co-location systems, the storage unit shares the grid connection with a generation facility—such as a PV system or wind turbines. The storage unit buffers excess electricity that would otherwise be fed into the grid at low or negative prices or curtailed, thereby avoiding curtailment losses. Sharing the grid connection optimizes its utilization and smooths out feed-in peaks—which stabilizes the local distribution grid. At the same time, the physical bundling of generation and storage reduces infrastructure and construction costs and minimizes the regulatory approval process. Where grid connection capacity is scarce, co-location is therefore often the most practical solution.
Green Energy Storage vs. Multi-Use: What the Storage System Is Allowed to Charge
The regulatory framework plays a key role in determining how flexibly a storage system can be used. A green electricity storage system may only draw electricity from renewable sources—it remains tied to the connected renewable energy generation facility, but in return ensures that facility’s eligibility for subsidies. Since the amendment to the Energy Economy Act (EnWG) (in effect since December 23, 2025), a multi-use or mixed-energy storage system may also draw a proportionate amount of grid electricity and assume additional market roles. This distinction is central to revenue planning: it determines which use cases and marketing channels are available.
Use Cases: When to Use Which Model
- On-site consumption and peak shaving: Storage at the business premises (co-located with the rooftop or ground-mounted system)—for companies with high, consistent electricity demand.
- Yield Optimization for Large Solar or Wind Farms: Co-location optimizes the marketing of the green electricity generated and boosts the IRR—for investor projects in the MW range.
- Pure market and system services operation: Stand-alone storage—when a dedicated grid connection is available and no generation is to be integrated.
The choice of model is not purely a technical issue, but rather one of site selection and marketing. Site planning for co-located storage facilities takes into account not only the grid connection situation but also the accessibility of the site and environmental risks. Logic Energy, as a corporate group, provides all the necessary expertise—from site acquisition and grid connection planning to cross-market optimization—from a single source.
4. Six sources of revenue instead of one
Sources of Investment Income
- Self-consumption —a storage system increases the self-consumption rate from 20–35% to 60–80%. Every kWh consumed on-site saves the commercial electricity rate of 16–31 ct/kWh (BDEW / wattline, February 2026)—roughly 2–4 times more valuable than the EEG feed-in tariff of 7.70 ct/kWh (partial feed-in up to 10 kWp, effective August 1, 2026).
- Peak shaving —with a power price of 80–200 EUR/kW/year and a peak reduction of 300 kW, this results in annual savings of 24,000–60,000 EUR. Typical payback period: 3–5 years.
- Grid Fee Exemption (Section 118(6) of the Energy Industry Act (EnWG))—Storage systems commissioned by August 2029 are exempt from grid fees on purchased electricity for 20 years. This exemption applies under current law; the Federal Network Agency may adopt different regulations (Section 118(6), sentence 12, of the Energy Industry Act (EnWG)).
Revenue Sources from Trading and Balancing Energy
- Day-Ahead Arbitrage —the ISEA Battery Revenue Index (RWTH Aachen) does not report arbitrage separately but includes it in the cross-market result; for a 2-hour system with two cycles per day, this stood at approximately 215,400 EUR/MW/year based on a rolling 365-day average (as of August 18, 2026).
- Balancing energy (FCR + aFRR) — combined: approximately 179,000 EUR/MW/year (enervis BESS Index / pv magazine, 2025/2026).
- Intraday trading and instantaneous reserve —the cross-market result of the ISEA Battery Revenue Index (FCR + aFRR + arbitrage) stood at approximately 215,400 EUR/MW/year as of August 18, 2026; the index is updated daily, and there is no fixed annual value.
5. Technology: LFP, Efficiency, and Battery Management System
LFP vs. NMC: Which cell chemistry is best for commercial storage systems?
Lithium iron phosphate (LFP) is the industry standard for stationary commercial applications: no thermal runaway (high safety), >6,000 to >10,000 charge cycles at 80% remaining capacity, stable operation between −20 °C and +60 °C, lower-cost raw materials (no cobalt), and a round-trip efficiency of 92–95%. BNEF reports system prices of $108/kWh (December 2025)—a 45% decrease compared to 2024.
NMC (Lithium-Nickel-Mangan-Kobalt) bietet höhere Energiedichte, hat aber geringere Zyklenlebensdauer (~3.000-5.000) und höhere Kosten durch Kobalt - in Großspeichern kaum noch relevant. Blei-Säure-Batterien spielen mit ~80 % Wirkungsgrad und <1.000 Zyklen keine wirtschaftliche Rolle mehr.
Efficiency: What is lost during charging and discharging
In modern LFP systems, the round-trip efficiency is 92–95%—out of every 100 kWh of solar power charged, 92–95 kWh are available again. With 365 charging cycles per year and a capacity of 1,000 kWh, annual losses amount to approximately 18,000–29,000 kWh. The inverter’s DC/AC efficiency is 97–99%; thermal management can reduce efficiency by 2–5 percentage points in warm environments.
Battery Management System (BMS): The brain of the storage system
The BMS monitors the voltage, current, and temperature of each cell and protects against overcharging, deep discharge, and short circuits; thermal management and fire protection are key safety factors in the operating concept. It handles cell balancing, state-of-charge (SoC) and state-of-health (SoH) estimation, and communication via CAN bus, Modbus, and SunSpec. Integrated into the higher-level energy management system (EMS), it controls charging and discharging. EERA Consulting (October 2025) documented that active cross-market optimization resulted in revenues up to 243% higher than with passive systems.
Smart Meters and Communication
As of June 1, 2026, all new PV systems with a capacity of 7 kW or more are required to have a smart meter (Solar Peak Act, in effect since February 25, 2025)—previously, the threshold was 25 kWp. The smart meter enables remote power curtailment (Section 14a of the Energy Industry Act), dynamic grid fees, and a transparent billing basis. For investors, it serves as an enabler for dynamic tariff models that can increase storage revenue by an estimated 3–8%.
6. Components of a Photovoltaic System with Storage
Lithium-ion batteries: The heart of energy storage
The battery cells are the most expensive component. Key specifications for commercial LFP systems: typical storage capacity per module of 50–250 kWh, >10,000 charge cycles at 80% residual capacity, service life of 10–15 years, system price of $108/kWh at the cell pack level (BNEF, December 2025). For most co-located PV projects (2-hour systems, C-rate 0.5), lithium-ion batteries are the superior choice; turnkey system prices per kWh decrease significantly as system capacity increases.
Battery-backed inverters: Connecting the PV system to the power grid
The storage inverter serves as the interface between the PV system, the battery storage, and the grid, handling AC/DC conversion, MPPT, grid forming (off-grid operation), and grid connection. Bidirectional inverters are predominantly used for commercial systems; their DC/AC efficiency ranges from 97% to 99%. Costs range from 50,000 to 200,000 EUR per power class (100 kW to 5 MW); in co-location projects starting at 1 MWp, inverters account for approximately 10–15% of the total investment.
Solar panels: Generating solar power
PV modules convert sunlight into electricity. High-efficiency monocrystalline modules are the most common choice for commercial systems: efficiency 21–23%, rated power 550–700 Wp, service life 25–30 years (80% of rated power after 25 years), degradation of ~0.3–0.5% per year, system costs (ground-mounted) 750–1,000 EUR/kWp. Bifacial modules generate 10–25% more energy on light-colored surfaces. For more on this specific system type, see our page on agri-PV.
Installation and Commissioning
The installation includes foundation work, module installation and DC cabling, setup of the storage containers, AC-side installation (grid connection, protective devices in accordance with VDE 0100), commissioning and parameterization (EMS/BMS, smart meter gateway), as well as handover of the grid connection and MaStR registration. The installation time for a 500 kWp + 400 kWh system is 4–8 weeks after approval; for multi-MWp ground-mounted systems, a construction period of 3–6 months should be planned.
7. Sizing: How large does a commercial PV storage system need to be?
Guidelines for Commercial PV Storage Systems
- Self-consumption: 0.8–1.2 kWh per kWp—500 kWp PV → 400–600 kWh of storage; self-consumption rate 60–80%.
- Peak Shaving: Storage capacity = 20–40% of the peak load to be shaved; capacity = power × duration (15–60 min.).
- Arbitrage / Revenue Stacking: C-rate 0.5–1.0 – 10 MW → 10–20 MWh (reference model from the 8Energies white paper).
Typical system sizes and investment costs by segment
Commercial PV system with storage (200–1,000 kWp): Annual generation ~180,000–900,000 kWh; recommended storage capacity 160–1,000 kWh; PV system costs (rooftop) 750–950 EUR/kWp; total investment for a rooftop system with storage 300,000 EUR–1.5 million EUR.
Industrial / ground-mounted PV with co-located storage (1–20 MWp): Storage capacity 1–20 MWh; total investment in PV + storage starting at ~5 million EUR. The specific system costs per kWh depend heavily on size and configuration and decrease significantly as the system size increases.
Which C-rate for which purpose?
- C-Rate 0.25 (4h): Day-Ahead Arbitrage, Long Load Shifting.
- C-Rate 0.5 (2h): Market standard for co-location—a balance between arbitrage and FCR.
- C-Rate 1.0 (1h): FCR and short-term intraday peaks.
- C-Rate 4.0 (15 min.): FCR prequalification.
Retrofitting vs. Redesign
A storage system planned from the outset is significantly more cost-effective than a retrofit: joint grid connection planning saves 50,000–150,000 EUR, inverter sizing can be optimized, permitting processes run in parallel, and the building code exemption (Section 35(1)(11) of the German Building Code (BauGB)) applies only if there is a spatial and functional connection. For existing systems with connection reserve capacity, the 8Energies white paper nevertheless estimates the IRR uplift at +6–24%.
8. For Businesses: Self-Consumption, Self-Sufficiency, and a 3-5 Year Payback Period
Total PV self-consumption in Germany rose from 3.55 TWh (2020) to 12.28 TWh (2024)—17% of net PV generation (Fraunhofer ISE, December 2025). Achievable figures: Self-consumption rate from ~25% to 60–80%; grid procurement can be reduced by 35–55 percentage points; electricity costs (16–31 ct/kWh for commercial electricity) can be reduced by thousands to hundreds of thousands of euros annually; self-sufficiency of 40–60% of annual electricity demand.
Peak Shaving: The Underestimated Lever
Companies pay a capacity charge based on their annual peak load—typically 80–200 EUR/kW/year. A manufacturing facility (800 kW → 500 kW) saves approximately 24,000 EUR/year at 80 EUR/kW; for a large consumer (2,000 kW peak load, 200 EUR/kW), grid fee savings of up to 400,000 EUR/year are possible.
Payback Periods Compared
| Constellation | Payback period |
|---|---|
| Commercial - PV Storage with Peak Shaving | 3–5 years |
| Commercial - PV + Storage (without peak shaving) | 5–8 years |
| Commercial - PV only (without storage) | 6–10 years |
Businesses planning to install their own PV system with integrated energy storage can find more information about project and financing models on the page " Your Own PV System for Your Business."
9. The Regulatory Window: 2026–2028
Exemption from grid fees (Section 118(6) of the Energy Industry Act)
The incentive applies to storage facilities that become operational within 18 years of August 4, 2011; the deadline is in August 2029. “Commissioning” is defined as the first draw of electricity for trial operation (Section 118(6), sentence 6, of the Energy Industry Act (EnWG)).
The exemption applies only to grid fees in the narrow sense, i.e., the transmission and capacity charges. It does not apply to statutory surcharges, the concession fee, metering point operation and billing, the electricity tax, or the construction cost subsidy (Federal Court of Justice, decision of June 20, 2017—EnVR 24/16). The value of the exemption in individual cases depends on the voltage level, grid area, and duration of use, and cannot be quantified on a flat-rate basis.
Regulatory reservation. The 20-year exemption is stipulated in the law, but does not constitute a guaranteed basis for calculation over the entire term. Pursuant to Section 118(6), sentence 12 of the Energy Industry Act (EnWG), the Federal Network Agency may adopt provisions that deviate from sentences 1 through 11—including, expressly, with respect to the temporal scope of application. This requires a determination procedure under Section 29(1) of the Energy Economy Act (EnWG); such a procedure is currently underway under file number GBK-25-01-1#3 (AgNes). In this proceeding, the Federal Network Agency has characterized the full exemption as not cost-reflective. There is no statutory grandfather clause, nor is there any case law on the issue of protection of legitimate expectations; in any case, the specialized literature considers it difficult to justify a legitimate expectation, at least for new installations . Treat the exemption as a bonus, not as a planning basis guaranteed for the entire term.
The exact deadline has not been uniformly specified: According to the calculation of the deadline under Sections 187(2) and 188(2) of the German Civil Code (BGB), the deadline ends at the close of business on August 3, 2029; documents from the Federal Network Agency cite August 4, 2029. There is no judicial clarification on this matter—those planning down to the exact day should use the earlier date.
KraftNAV Exemption and Grid Integration
Since December 2025, battery storage systems have been exempt from the complex KraftNAV procedure; co-located storage systems benefit from the priority connection granted to renewable energy installations under Section 8 of the EEG. Conversely, systems with a capacity of 100 kW or more—both generation facilities and storage systems—are integrated into the grid operators’ congestion management system via Redispatch 2.0. For co-location, this means that the storage system can smooth out feed-in peaks and actively contribute to system stability and to relieving the load on the distribution grid.
Special Provisions Under Building Law (Section 35(1)(11) of the German Building Code (BauGB))
Co-located storage facilities that are spatially and functionally connected to an existing renewable energy plant are granted special status under building codes for outdoor areas—no zoning plan is required. This significantly speeds up the permitting process for open-space facilities.
EEG 2027: Fixed feed-in tariff no longer applies to new installations
On July 29, 2026, the Federal Cabinet approved the government’s draft of the EEG 2027 along with the grid connection package. For new photovoltaic systems, the fixed feed-in tariff is to be eliminated and replaced by a time-limited transitional payment; direct marketing will become the norm. The draft is not yet legally binding—the Bundestag and Bundesrat will deliberate on it after the summer recess, and it is scheduled to take effect on January 1, 2027. Systems that go into operation by the end of 2026 will retain their guaranteed 20-year feed-in tariff. For pure PV systems without storage, this increases the risk of revenue loss and curtailment—a further incentive to integrate solar storage from the outset. Details can be found in the guide to EEG feed-in tariffs for 2026.
10. Tax Benefits: 30% declining-balance depreciation for battery storage systems
The Act to Strengthen Germany as a Business Location (approved by the Bundesrat in July 2025) raised the declining-balance depreciation rate under Section 7(2) of the Income Tax Act (EStG) to three times the straight-line rate, up to a maximum of 30 percent.
- Battery storage (useful life: 10 years): declining-balance depreciation of 30% (3 x 10%), valid from July 1, 2025, through December 31, 2027.
- Solar power system (useful life of 20 years): declining-balance depreciation of 15% (3 × 5%, Section 7(2) of the German Income Tax Act (EStG)).
The investment deduction (50%, Section 7g(1) of the Income Tax Act), special depreciation (40%, Section 7g(5) of the Income Tax Act), and declining-balance depreciation may be combined. Depreciation on a declining-balance basis is calculated in the year of acquisition on the full tax base reduced by the investment deduction; the special depreciation reduces the remaining book value only in subsequent years. This results in a large block of expenses in the first one to two years—the exact amount depends on the individual situation. See the article on “Saving on Photovoltaic Taxes in 2026” for details.
Note: The tax implications depend on your individual tax situation. You should consult a tax advisor to determine whether this applies to you.
11. Are there any incentive programs for PV storage systems?
KfW Loan 270: Financing for PV Systems and Storage
The KfW program “Renewable Energies – Standard” (270) is the most important financing instrument for commercial PV systems. Loan amounts of up to 150 million euros per project, terms of 5 to 30 years with grace periods, interest rates starting at approximately 3.8% effective, depending on creditworthiness and term (best credit rating; KfW publishes daily updated terms as of August 2026), with a financing ratio of up to 100% of eligible costs. Eligible costs include solar systems, battery storage, inverters, installation, and grid connection. Applications must be submitted through the borrower’s primary bank before construction begins.
State-level incentive programs for energy storage systems
Several federal states offer subsidies for the purchase and installation of energy storage systems: Bavaria (BayernLabo and regional programs), Baden-Württemberg (L-Bank Environmental Loan Program), Thuringia, Saxony, and Brandenburg (investment grants from state development agencies). The grants can range from several hundred to several thousand euros; most programs require an application to be submitted before the purchase, and funds are often exhausted quickly.
Compensation, Market Premium, and Bids
- EEG Market Premium: Solar systems of 100 kW or more receive a sliding-scale market premium through their direct marketing partner. The EEG feed-in tariff for systems up to 100 kW is 7.70 ct/kWh (partial feed-in up to 10 kWp, effective August 1, 2026, valid through January 31, 2027). Read more in the article on the 2026 EEG feed-in tariff.
- The Federal Network Agency's innovation tenders specifically promote combinations of renewable generation and storage facilities—which is relevant for co-location projects in the tender segment.
- Declining-balance depreciation and IAB: A significant portion of the investment in storage is tax-deductible in the first few years.
Conclusion: Plan for co-location from the very beginning
Today, storage is no longer just an add-on—it’s an integral part of the return-on-investment structure. As a group of companies, Logic Energy designs and builds combined PV-storage systems as a one-stop solution—from site analysis and land acquisition to ongoing operations. Whether you’re an investor interested in a co-location project, a business looking to reduce electricity costs with your own PV system, or interested in the current EEG feed-in tariff or tax incentives: Contact us—we’ll calculate your individual potential free of charge.
This article is intended solely for general information purposes and does not constitute investment, tax, or legal advice. Return figures are based on historical data from the Helm Group and on cited third-party market studies; they are not a guarantee of future results. Technical specifications are approximate and depend on the product, operation, and location. For your specific situation, please consult a licensed financial or tax advisor. Legal provisions and procedures are current as of August 2026 and are subject to change; ongoing regulatory proceedings, such as AgNes (Federal Network Agency), may alter the framework conditions described. All information is provided without warranty. As of August 2026.
FAQ
What does "co-location" mean in the context of battery storage systems?
What is the difference between colocation and stand-alone storage?
Is a solar storage system worth it for a commercial business?
What return can a co-located solar storage system generate?
Does the grid fee exemption also apply to co-located storage facilities?
What is the difference between LFP and NMC in PV storage systems?
How many sources of revenue does a solar storage system have in Germany?
When does the 30% declining balance depreciation for battery storage systems end?
References
- 8Energies, enspired, and GOLDBECK SOLAR – White Paper “Co-located Gray Energy Storage: Business Case, Optimization, and Integration,” February 20, 2026
- pv magazine – Co-location: Grid-connected storage increases the internal rate of return on solar power projects by up to 29 percent, February 23, 2026
- ISEA Battery Revenue Index, RWTH Aachen – rolling 365-day average, accessed August 18, 2026
- pv magazine – 6.57 GWh of New Battery Storage Capacity by 2025 (RWTH Aachen / ISEA), January 8, 2026
- BSW-Solar – Battery Storage Capacity to Increase Fivefold Within Five Years, January 12, 2026
- pv magazine – Co-location: Grid-connected storage increases internal rate of return by up to 29 percent, February 23, 2026
- Solarserver – White Paper: Co-location with Battery Storage Ensures the Profitability of Solar Parks, February 23, 2026
- FfE – German electricity prices on the EPEX Spot exchange in 2025 and 2026
- Bloomberg – Europe Saw a Record Surge in Negative Electricity Prices in 2025, January 5, 2026
- pv magazine – Battery Storage 2026: From Boom to Infrastructure, January 7, 2026
- Solarserver – BNetzA Figures on Grid Connection Requests for Large-Scale Storage Systems, November 2025
- Modo Energy – Germany Battery Expansion Report, August 2025
- pv magazine – BNEF: Prices for lithium-ion battery storage fall to $108 per kilowatt-hour, December 9, 2025
- ESS News / enervis – Enervis Battery Storage Index, January 28, 2026
- EERA Consulting – Revenue from Co-Located Battery Storage Systems, October 2025
- pv magazine – Grid connection procedures for battery storage systems of 100 MW or more will no longer follow KraftNAV, December 19, 2025
- Fraunhofer ISE – Self-Consumption of Solar Power Rises Sharply, December 4, 2025
- pv magazine – Cabinet Approves Drafts of the EEG 2027 and Grid Package, July 29, 2026
- Federal Network Agency – EEG Subsidies and Rates (Feed-in Tariffs effective August 1, 2026), accessed August 4, 2026
- Rystad Energy – Economic Outlook for Europe's Battery Storage Under a New Pricing Structure, 2025/2026
All information is provided without guarantee. As of August 2026.